Dennis Clements, Chief Electrical Inspector at the Oregon Building Code Department created an overview of the state’s efforts to streamline the permitting process, by offering permits through an online program. Download this document here.

Minor Installation Label:

  • Original minor label program was used by electrical contractors for installation of branch circuits up to 30 amps at 240 volts.
  • EVSE installations require 40 amp 240 volt circuit
  • Minor installation label will be extended to include EVSE installations in one or two family dwellings, in attached garages.
  • 9 out of 10 installations will not be inspected under minor installation label

Also, download here a press release, which explains Oregon’s Building Code Division’s permitting process for home charging units.